This project includes road widening, traffic signal installation, construction of railroad crossings, installing appropriate drainage, curb, gutters, and sidewalks on Lake Washington Boulevard North from Park Avenue North to Coulon Park. This project will serve the Southport development adjacent to Coulon Park and improve access to the park.
The developer of the site adjacent Coulon Park is to design and build these improvements and in turn receive credit toward their traffic mitigation contribution. The developer is completing this in three phases. The railroad crossing is complete except for the signal start-up requirements. The project schedule is pending the developer's continuing construction on the site.
$950,000 programmed into 2014-2015. A large portion is unfunded, however, until the developer has a definite schedule to build their office building.